# The meeting is over. Here is the action plan.

AT Learn practice project. An example of applying skills, not a client outcome.

## Source facts
Practice meeting: Anna delivers the copy on 6 November. The layout takes two working days after the copy arrives. Ilya tests the form after the layout. Budget and launch date are not agreed.

## Record
Anna → copy → 6 November. Ilya → form test → after the layout.

## Connect tasks
Copy → two working days for layout → form test → launch decision.

## Clarify
Who owns the layout? What is the budget? When will launch be agreed?

## Review
- [ ] Layout timing starts when the copy arrives
- [ ] Launch is not described as agreed
- [ ] Each assigned task keeps its owner